| 1 |
The Malayala Manorama Co. Ltd. (10 Projects) Quilon, Cochin,Trivandrum, Thrissur, Palakkad, Malappuram, Calicut,Kannur , Alappuzha, Pathanamthitta |
Design ,Supply, Erection,Testing and Commissioning of 10 CMD, 15 CMD & 55 CMD Effluent Treatment Plant across 10 printing Press units |
|
| 2 |
Milma, Kottayam |
Revamping and expansion of effluent treatment plant suitable to handle 150-cum/day capacity at Kottayam Dairy |
|
| 3 |
Milma, Naduvattom |
Up-gradation of existing Effluent Treatment Plant of capacity 60m3/day |
|
| 4 |
Milma, Vadakara |
Design, Supply, Erection and Commissioning of ETP 10m3/day |
|
| 5 |
Milma, Edappaly |
Construction, Erection and Commissioning of 60 cum/day capacity ETP at Edappaly |
|
| 6 |
Milma, Chalakudy |
Setting up Effluent Treatment Plant of 30 m3/day capacity |
|
| 7 |
Milma, Kasaragod |
Up gradation of existing Effluent Treatment plant to 100 m3/day |
|
| 8 |
Mathrubhumi Printing and Publications Co. Ltd., Manjummel |
Design Supply Erection and Commissioning of Effluent Treatment Plant of 15 CMD |
|
| 9 |
Sea Food Park (India) Limited, Aroor |
Revamping of Existing Effluent Treatment Plant of 250 CMD |
|
| 10 |
Synthite Industries Pvt Ltd., Kolenchery |
Design, Supply, Erection and Commissioning of ETP 20m3/day |
|
| 11 |
MRF Limited, Kottayam |
Up gradation of ETP, 400KLD |
|
| 12 |
Southern Railway, Diesel loco shed, Ernakulam |
Design, Fabrication, Supply and Commissioning for ETP 52 m3/day |
|
| 13 |
MEPZ-SEZ, Chennai, C/o KITCO, Cochin |
Trouble shooting and operation of the STP 1000 m3/day using MBBR Technology |
|
| 14 |
CETP, C/o KITCO, Cochin |
Enhancement of Capacity of Common ETP 1800 m3 /day |
|
| 15 |
TEXFED, Calicut |
Turnkey Execution for ETP of 60m3/day with MBBR Technology |
|
| 16 |
Kodungallur Municipality |
Turnkey Execution for ETP 30 m3/day with MBBR Technology |
|
| 17 |
Kodungallur Municipality |
Turnkey Execution for ETP 30 m3/day with MBBR Technology |
|
| 18 |
Inter Market India (P) Ltd., Perundurai |
Design, Supply, and Commissioning of Mechanical Equipment for ETP 400m3/day-MBBR Technology |
|
| 19 |
Jayabalaji Dyeing, Erode |
Design, Supply, and Commissioning of Mechanical Equipment for ETP 600m3/day |
|
| 20 |
Janson Textile Processors, Thiruchengode, Tamil Nadu |
Consultant for the modernization of ETP for 500m3/day and commissioned the system successfully |
|
| 21 |
William Good Acre & Sons India (P) Ltd., Alappuzha |
Civil work and Supply, and Commissioning of ETP 100 m3 / day |
|
| 22 |
Golden Sun Industries, Perundurai |
Design, Supply, and Commissioning of Mechanical Equipment for ETP of 60m3/day |
|
| 23 |
Theni Guru Krishna Textile Mills |
Supply, Installation and Commissioning of Mechanical Equipment for ETP 200m3/day |
|
| 24 |
Coco Tufters (P) Ltd., Tuticorin |
Fabrication, Supply, and Commissioning of Mechanical Equipment for ETP 30m3/day |
|
| 25 |
Sharada Terry Products Ltd. |
Modification of existing Plant of Mechanical Equipment for capacity 2400 m3/day |
|
| 26 |
Merchem, Eloor |
Fabrication, Supply, Installation, Commissioning and Study on Pilot plant |
|
| 27 |
Bannari Amman Spinning Mills Ltd., Coimbatore |
Design, Supply, and Commissioning of Mechanical Equipment for ETP 80m3/day |
|
| 28 |
Inter Market India (P) Ltd., Perundurai |
Design, Supply, and Commissioning of Mechanical Equipment for ETP 400m3/day-MBBR Technology |
|
| 29 |
Bharati Shipyard Limited, Mumbai |
Design, Fabrication, Supply and Commissioning of Mechanical Equipment for STP 51 m3/day |
|
| 30 |
TEBMA shipyard, Udupi, Karnataka |
Design, Supply and Commissioning of Mechanical Equipment for STP 50 m3/day |
|
| 31 |
Plant Lipids (P) Ltd., Kolenchery |
Revamping of existing ETP for capacity of 120m3/day |
|
| 32 |
Aromatic Ingredients (P) Ltd., Kolenchery |
Design, Supply, Erection and Commissioning of ETP 40m3/day |
|
| 33 |
KLD Board Ltd., Hi-Tech Dairy, Kulathupuzha |
Design, Supply, Erection and Commissioning of ETP 15m3/day |
|
| 34 |
KLD Board Ltd., Hi-Tech Dairy, Mattupatty |
Design, Supply, Erection and Commissioning of ETP 15m3/day |
|
| 35 |
Oil Palm India Ltd., Modern Rice Mill, Vechoor |
Design, Supply, Erection and Commissioning of ETP 40m3/day |
|
| 36 |
ATK, Perundurai |
Design, Supply, Erection and Commissioning of Effluent Treatment Plant (Upgradation) |
|
| 37 |
Plant Lipids, Srilanka |
Design, Supply, Erection and Commissioning of 40 CMD Effluent Treatment Plant |
|
| 38 |
MM Publications, Kottayam |
Construction and Commissioning of Primary Treatment Plant at KINFRA Textile Centre of capacity 200 CMD |
|
| 39 |
KINFRA Textile Centre, Kannur |
Construction and Commissioning of Primary Treatment Plant at KINFRA Textile Centre of capacity 200 CMD |
|
| 40 |
Primus gloves |
Construction and Commissioning OF ETP of 80 CMD capacity |
|
| 41 |
Vittal Agro Industries |
Construction and Commissioning of ETP at Vittal Agro Industries of 40 CMD |
|
| 42 |
Kerala Khadi and Village Association, Ollur |
Construction and Commissioning of 30KLD textile effluent treatment plant |
|
| 43 |
Akay Spices Pvt. Ltd., Perumbavoor |
Design, Supply, Erection and Commissioning of Effluent Treatment Plant of Capacity 40 CMD |
|
| 44 |
St.Antony’s Jewellery Works, Thrissur |
Design, Supply, Erection and Commissioning of Effluent Treatment Plant of Capacity 20 CMD |
|
| 45 |
Malabar Gold Pvt. Ltd., Kakkancherry |
Design and estimation of Effluent Treatment Plant of Capacity 60CMD with ultra filtration system |
|
| 46 |
HEMPEL Paints Qatar,Kuwait & Jeddah |
Design, Supply, Erection and Commissioning of Effluent Treatment Plant of Capacity 16CMD& 52 CMD |
|
| 47 |
Arjuna Natural Extracts Ltd., Edayar |
Design, Supply, Erection and Commissioning of Effluent Treatment Plant of Capacity 20 CMD |
|
| 48 |
Cloud Chemicals, Edayar |
Design, Supply, Erection and Commissioning of Effluent Treatment Plant of 5 CMD |
|
| 49 |
HLL Life Care Limited, Irapuram |
Design, Fabrication, Supply and Commissioning of Primary Effluent Treatment Plant |
|
| 50 |
Ridha Polymers, Edayar |
Design, Supply, Erection and Commissioning of Effluent Treatment Plant of 5 CMD |
|
| 51 |
MARDEC R. K. Golden Rubbers, Edayar |
Up gradation of exsisting Effluent Treatment plant to 300 KLD |
|
| 52 |
Alwaye Rubbex Rubber Pvt. Ltd., Desom |
Revamping of existing Effluent Treatment plant to 300 KLD |
|
| 53 |
Sabari Cottons International, Nadukkani |
Design, Supply, Erection and Commissioning of Effluent Treatment Plant of 200 CMD |
|
| 54 |
Organo Fertilizers India Pvt.Ltd., Edayar |
Design, Supply, Erection and Commissioning of Effluent Treatment Plant of 10 CMD |
|
| 55 |
Akay Flavours and Aromatics Pvt.Ltd., Perumbavoor |
Design Supply Erection and Commissioning of Effluent Treatment Plant of 25CMD |
|
| 56 |
CETP – KINFRA Nellad |
Augmentation of CETP ( electro – mechanical) at KINFRA Smal industries Park at nellad |
|
| 57 |
TMV Natural Extracts, Edayar |
Design Supply Erection and Commissioning of Effluent Treatment Plant of 7CMD |
|
| 58 |
SSK Polymers, Alwaye |
Design Supply Erection and Commissioning of Effluent Treatment Plant of 100 CMD |
|
| 59 |
Green Leaf Extracts, Kalamassery |
Design Supply Erection and Commissioning of Effluent Treatment Plant of 7 CMD |
|
| 60 |
Malabar Latex, Athani |
Revamping and up-gradation of Effluent Treatment Plant of 20 CMD |
|
| 61 |
Mascot Frozen Foods (P) Ltd., Marathakkara |
Revamping and up-gradation of Effluent Treatment Plant of 20 CMD |
|
| 62 |
SIDCO, Athani |
Erection and commissioning of Effluent Treatment Plant |
|
| 63 |
Common Effluent Treatment Plant for Aroor-Chandiroor Puthanthodu by INKEL limited |
Design Construction Supply Erection and Commissioning of Effluent Treatment Plant of 1500 CMD |
|